ORDER N0. 16213 APPROVAL OF REQUEST OF CONTRACTOR, CLARK & STROMAN CONSTRUCTION, INC., FOR PAYMENT NO. I, FOR CONSTRUCTION OF THE NEW COUNTY COURT AT LAW COURTROOM AND OFFICES AND MODIFICATION OF THE EXISTING TAX ASSESSOR-COLLECTOR'S OFFICE On this the 12th day of August 1985, upon motion made by Commissioner Lich, seconded by Commissioner Holland, the Court unanimously approved the request of Contractor, Clark & Stroman, Inc., for Payment No. 1, for Construction of the New County Court at Law Courtroom and Offices and Modification of the Existing Tax Assessor-Collector's Office, in the amount of $8,077.85, as examined by Architects, Schubert & Williams, Inc. and recommended to the Court that payment be made. It is ordered by the Court that the County Treasurer and. County Auditor be authorized to draw a voucher on the Revenue Sharing Trust Fund in the amount of $8,077.85, payable to Clark & Stroman Construction, Inc. (CATION AND CERTIFICATE FOR PAYMENT AIA DOCUMENT G702 P.1GE ONE OF 'L PAGES TO (owner): The County of Rerr PROJECT: New CourtrooEnf~& Offices APPLICATION NO: ~ Distribution to: Rerr County Courthouse Rerr County Courthouse PERIOD FROM: 7-'J8-85 ^ OWNER Kerrville, Texas 78028 Kerrville, Texas 8-1-85 TO ^ ARCHITECT : ^ CONTRACTOR ATTENTION: CONTRACT FOR: ARCHITECT'S ^ PROJECT NO: CONTRACT DATE: sjUly 8. 1985 CONTRACTOR'S APPLICATION FOR PAYMENT ,CHANT GE ORDER SUMMARY Change Orders approved in previous months by Owner TOTAL ADDITIONS DEDUCTIONS Approv ed this .Month Number Date Approved TOTALS / • Net change by Change Orders The undersigned Contractor certifies that to the best of his knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Docu- ments, that all amounts have been paid by him for 6Nork for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due. CONTRACTOR: Clark & StrOIDari Construction, By: Date: ~- F/r Application is made for Payment, as shown below, in connection with the Contract. Continuation Sheet, AIA Document G703, is attached. The present status of the account for this Contract is as follows: ORIGINAL CONTRACT SUM ...:.................. . $ 119.900.00 Net change by Change Orders ..................... CONTRACT SUM TO DATE ........................ S ~ ~ 9.900.00 TOTAL COMPLETED & STORED TO DATE ........... $ 8, 503.00 (Column G on G703) - RETAINAGE ~_% ......................... $ 425. ~ 5 __ or total in Column I on G703 • TOTAL EARNED LESS RETAINAGE .................. $ 8.077.85 LESS PREVIOUS CERTIFICATES FOR PAYMENT ....... CURRENT PAYMENT DUE ......................... $ 8.077.85 • 1nC. State of: ~'R-~CaS County of: i~~^SD-~i Subscribed and sworn to before me Is 3 j day of S _ t , 19 x'S Notary Public:-S ~-<<~ C . iZ~~ '~L .~ 7 My Commission expires: 3,~q _ ~g ARCHITECT'S CERTIFICATE FOR PAYMENT In accordance with the Contract Documents, based on on-site obser- vations and the data comprising the above application, the Architect certifies to the Osaner that the Work has progressed to the point indicated; that to the best of his knowledge, information and belief, the quality oP the Work is in accordance with the Contract Docu- ments; and that the Contractor is entitled to payment of the AMOUNT CERTIFIED. LED .............................$ if amount certified differs from the amount applied Ior.) /1 a °i •/ ~ 9 Q ~ By: // r Date: v ~/y a'S This Cer ficate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named erein. Issuance, payment and acceptance of payment are without prejudice to any rights f the Owner or Contractor under this Contract AIA DOCUMENT 6702 APPLICATION AND CERTIFICATE fOR PAYMENT • APRIL 1978 EDITION • AIAa • ~ 1978 THE AMERICAN INSTITUTE OF ARCHITECTS, 173i NEW YORK AVENUE, N.W., \VASHINGTON; D.C. '_0006 G702-1978 .lINUATION SHEET AlA DOCUhfENT 6703 PAGE f)f 9 P>GE> AIA Document G702. APPLICATION AND CERTIFICATE FOR PAY\fENT, containing APPLICATION NUAI6ER: 1 Contractor's signed Certification is attached. APPLICATION DATE• $_ 1-gf In tabulations below, amounts are stated to the nearest dollar. PERIOD FRO~A: 7-1$-85 L'>e Column 1 on Contracts where variable retainage For line items may apply. TO: 8-1-85 ..ARCHITECT'S PROTECT NO: A 8 C O E F G H I \VORK CO~~iPLETED 0T 4L CO \1PLETEO RE~1 .~'o, DESCRIPTION OF WORK SCHEO ULED VALUE This Application . . AHD STORED >o BALANCE TO FINISH RETA~HAGE Previous Applications Work in Place Store) Materials TO DATE tD+E+F) (G=C1 I K-G) (not in D or E) 1. Electric 14,912.70 990.00 _ 990.00 7% 13,922.70 2, Heating & Air 12,936.00 ------- ------ 12,936.00 3. Plumbing 3,300.00 ------- ------ 3,300.00 4. Painting,Wallcover 11,000,00 ------- ------ 11,000,00 5. .Flooring 7,012.50 ------- ------ 7,012.50 6. Inaulation,Drywall 10,615.00 1650.00 1650.00 1696 8,965.00 7. Ceilings 13,590.50 ------- ------- 13,590.50 8, Glass & Glazing 1,094.50 ------- ------- 1,094.50 9. Cabineta,Credenza 3,242.80 ------- ------- 3,242.80 10, Countertops 2,047.10 ------- ------- 2,047.10 11. Materials 19,794.63 220,00 220.00 19b 19,574.63 12, I,abor,Supervision 17,711.7 3000.00 3000.00 1796 14,711.27 Bond 2,371.00 2371,00 2371.00 0096 --------- Permit 272.00 .: 272.00 - _ 272.00 0096 --------- I I i ~. .. I I ( f 19 00.001 8503.00 I 8503.00 111 397.0 ( AIA DOCUMENT 6703 • CONTINUATION SHEET APRIL 7918 fDiTION AIA .• 2 1978 THE AMERICAN INSTITUTE OF ARCHITECTS, 1731 NEW YORK AVE., N.tV., IVASHINDTON, D.C. 10006 G7D3 -1978