ORDER NO. 16336 APPROVAL OF CHANGE ORDER NO. TWO AND CHANGE ORDER NO. THREE TO CONTRACT WITH CLARK & STROMAN CONSTRUCTION, INC. FOR THE NEW COUNTY COURT-AT-LAW COURTROOM AND OFFICES AND MODIFICATION OF EXISTING TAX ASSESSOR-COLLECTOR'S OFFICE On this the 15th day of October 1985, upon motion made by Commis- sioner Holland, seconded by Commissioner Higgins, the Court unanimously approved Change Order No. Two and Change Order No. Three, to the Contract with Clark & Stroman Construction, Inc., for the new County Court-at-Law Courtroom and Offices and Modifica- tion of the Existing Tax Assessor-Collector's Office, and as recommended by Schubert & Williams, Inc., Architect, as follows: Change Order No. Two - Construct and install new bookshelves in Judge's Chamber 105 as specified and in accordance with attached drawings in the amount of $866.00, and Change Order No. Three - Install auxiliary float switches in the two "Auxiliary Drain Pans" indicated on Drawing Sheet M-1 and cap the 3/4" secondary drain pipes so that they do not protrude through the ceiling. These switches shall be wired to the air conditioning power supply so that the unit goes off when the "Auxiliary Drain Pans" begins to fill, - in the amount of $70.00. CHANGE Distribution to: ORDER ° cHiT A ECT AIA DOCUMEN T G701 CONTRACTOR ~ FIELD ^ OTHER ^ PROIECT: NEW COURTROOMS & OFFICES (name, address) Kerr County Cour thouse Kerrville, Texas 78208 TO (Con[ractorrl 1 CHANGE ORDER NUMBER Tcoo (2) INITIATION DATE: October 9, 1985 ARCHITECT'S PROJECT NO: Clark & Stroman Construction,~c{ONTRACT FOR: General Construction P.O. Box 778 Boerne, Texas 78006 CONTRACT DATE: July 8, 1985 You are directed to make the following changes in this Contract: Construct and install new bookshelves in Judges Chamber lOS as specified and in accordance with the attached drawings for $866.00. ~1 3 No[ valid until +igned by both the Om~ner and Architect. Signature of the Contractor indicate. hk agreement herewith, mcludmg any adju.tment in thr G~n tract tium or Cunlract Time The original (Contract Sum) (6aarartteed ivtaxirn am{vst) was ......... ............. .... $ 119,900.00 Net change by previously authorized Change Orders ............................... .... $ 3 , 520.00 The (Contract Sum) (6va2nteed-folaximnm-East) prior to this Change Order was ..... .... $ 123 , 420.00 The (Contract Sum) (Gvararrteed-totazilrlvrrrEost) will be (increased) (decreased) (untFtattgetf) by this Change Order ................................................ .... .... $ 866.00 The new (Contract Sum) (C.DahKr~ec~d-Ma~EirrwarEesi) including this Change Order will be . $ 124,286.00 , The Contract Time will be (incseased) (decreased) (unchanged) by Zero ( -0-)Days. The Date of Substantial Completion as of the date of this Change Order therefore is Authorized: SCHUBERT & WILLIAMS, INC. CLARK & STROMAN CONST.,INC. THE COUNTY OF KERR _ ARCEllTECT on Suite 200 ~yoNiRA Box 778 l l > C p KerrRC urt use Ad re Address d S An onio, Texas 78205 Boerne, Texas 78006 Address Kerr i 78028 ~ F n- _ ~y~/ ( /J~~j~~ r ^ ~ xNf~ ~ BYE BY • • BY J~ ,~// 6 / / D (~/T~ bS DATP ~. - DT lO-1S-HS A A DOCUMENT 6701 CHANGE ORDER APRIL 197ft EDITION Aln" r8 197A THE AMERICAN INSTITUTE OF ARCHITECTS, 1715 NEW YORK AVE, N.W., Av~SHINGTON, D C 30flUb C7U1 - 1978 6 ~- O'~ I DNAVt l~hl Mff~' ,~, CeMI-i. ~iPW1G fi ~F '14~ -~~ ~ ~ ~~ ~~~ tb~ ~ 1YRx- ~ rio-{ I 9 ~~ '~ ~ . ~ `a~tiKr1 b -~ ~ L J rIMKFI oHt~DG - M1ry~ BeM~51Dt5 y~ ~~ r i ++J l V; ~~ '~~ itYlA*'~If'~ BOOKSHELF SECTION CHANGE Distribution to ' °~ ORDER OWNER ARCHITECT ® I E'9 AIA DOCUMENT G707 CONTRACTOR FIELD ^ OTHER ^ PROIECT: NEW COURTROOMS & OFFICES CHANGE ORDER NUMBER Three (3) (name, address) Kerr County Courthouse Kerrville, Texas 78028 INITIATION DATE: October 9, 1985 TO (Contractor): ARCHITECT'S PROJECT NO Clark & Stroman Const., Inc. CONTRACT FOR General Construction P.O. Box 778 Boerne, Texas 78006 CONTRACT DATE: July 8, 1985 You are directed to make the following changes in this Contract Install auxiliary float switches in the two "Auxiliary Drain Pans" indicated on Drawing Sheet M-1 and cap the 3/4" secondary drain pipes so that they do not protrude through the ceiling. These switches shall be wired to the air conditioning power supply so that the unit goes off when the "Auxiliary Drain Pans" begins to fill. Add $70.00 to the Contract for-this Work. Not valid until signed by both the Owner and Architect. Signature of [he Contractor indicates his agreement herewith, including any adlmtment in the Co ntract Sum or Contract Time The original (Contract Suml fL+wranteed-l+4aaciQUUraCosi) was ...................... ..... $ 119, 900.00 , Net change by previously authorized Change Orders .............................. .. .. $ 4, 386.00 The (Contract Sum) (Guaaxriead bt.asisruuu LosU prior to this Change Order was ..... ..... $ 124,286.00 . The (Contract Suml (Guam rateod A4axxuum~osU will be (increased) (deESeased) IriACalaegetl) by this Change Order .................. ................................. ..... $ 70.00 The new (Contract Suml (Guaranteed blasirnurn Lncq including this Change Order will be ... $ 124, 356.00 The Contract Time will be (increased) (decueaced) (unchanged) by Zero ( 0 )Days. The Date of Substantial Completion as of the date of this Change Order therefore is q~~h~ ~7 r~ SCHUBERTI& WILLIAMS, INC. CLARK & STROMAN CONST.,INC. ~~SUN THE TY OF KERR ARCyITECT CONTRACTOR OWNER 117 Ca n Suite 200 P.O. Box 778 Kerr Co Co se Addre r Addre~~ Address S Ant io Texas 78205 Boerne, Texas 78006 Kerrv' e 78028 E g ..000/4It/ BY ' BY~~~(tL y D D'~X-gs' D ~/ DATE -LS-HS A DOCUMENT 6701 CHANGE ORDER ANRIL 197f5 EDITION AIA" ~- 197f4 1978 701 HE AMERICAN INSTITUTE OF ARCHITECTS, 17is NEW VURK AVE, N.W., WASHINGTON, D C ?Of1aL - 6 CLARK & STROMAN CONSTRUCTION, INC. BUILDING CONTRACTORS P. O. BO% 778 BOERNE, TEXAS 78006 JOE CLARK WALTER STROMAN (512) 2d9-9351 pctober 2, 1985 ~ohn Williams chubert & Williams 115 Camaron St. San Antonio, Texas 78205 RECEIVED ocr ~ t9o~ As per our conversation on the drains off of the auxiliary pans, we hereby propose to furnish and install float switches that will cut off power to the equipment when the auxiliary pan gathers enough water to create an overflow of this pan to the ceil- ing. When the air conditioning is not working this should be the first thing to check. mhen you know you have a blockage of the drain pan which is a part of the air handling equipment. ?f these float switches are installed during the course of work that is presently in progress at the Kerr County Courtroom, we can do this for a sum of Seventy Dollars 070.00). Sincerely, Joe A. Clark L~Cki>Zh% JAC/mc