ORDER NO. 18066 APPROVAL OF CHANGE ORDER NUMBER 1 WITH H & H MATERIALS, INC. FOR THE REHABILITATION OF RUNWAY 02/20, LOUIS SCHREINER FIELD KC 88-02 IN CONCURRENCE WITH THE CITY OF KERRVILLE AND AUTHORIZATION TO SIGN THE CHANGE ORDER IN THE AMOUNT OF $12,708.50 On this the 25th day of August 1988, upon motion made by Commissioner Ray, seconded by Commissioner Holland, the Court unanimously approved the change of Order Number 1 with H & H Materials, Inc. for the rehabilitation of Runway 02/20, Louis Schreiner Field KC 88-02 in Con- currence with the City of Kerrville and Authorization to sign the change order in the amount of $12,708.50. ~iOI CLAY STREET ~ ~..~ KERRVILLE TEXAS 78028 512/896.7080 ~., ', ~fi ~Ce~P~llNC~ ~~ -~ 1 H & H Materials, Inc. Au,~ i2, //~-~ HAnJ l~e~~FUar ~,~ DISTRIBUTORS AND APPLICATORS OF FIBERGLASS CONCRETE PAINT SANDBLASTING & STEEL BRIDGE PAINTING LINSEED OIL APPLICATION WATERPROOFING AUGUST 10, 1988 CITY OF KERRVILLE ENGINEERING DEPARTMENT 800 JUNCTION HIGHWAY KERRVILLE, TEXAS 78028 ATTN: MR. JOE MACEIRAS> CITY ENGINEER GENTLEMEN: RE: PROJECT KC 88-02 REHABILITATION OF RUNWAY 02/20 - LOUIS SCHREINER FIELD, KERRVILLE IN CONNECTION WITH THE ABOVE REFERENCED PROJECT, WE PROPOSE TO FURNISH ALL LABOR, MATERIALS AND EQUIPMENT NECESSARY TO COMPLETE CERTAIN IMPROVEMENTS AND CORRECTIONS, PER PLANS AND SPECIFICATTnmc AC PRnVTTFT_ FnR THF. RnT.T.nvTNr. CnNSTT1F.R ATTnNS: 1 PyrcRose Orc~tr ChaN, ~rde No. Il 2 FOR REMOVAL OF 1}" ASPHALT PAVING INCLUDING NECESSARY SAW CUTTING AND FOR REMOVAL OF 6" FLEX BASE ONE LUMP SUM li 3 FOR 6" REINFORCED CONCRETE PAVING APPROXIMATELY 3618 SF @ 2.50/SF 11 4 FOR 1}" HOT MIX ASPHALT PAVING ON TOP OF b" CONCRETE PAVING APPROXIMATELY 3618 SF @ 0.75/SF $ 950.00 $ 9,045.00 ~/2,yo8r~ $ 2,713.50 THE QUANTITIES ABOVE ARE ESTIMATED ONLY. FINAL PAYMENT WOULD BE MADE ON ACTUAL MEASURED QUANTITIES. ITEM li 1 PAVEMENT MARKING TO MEET THE REQUIREMENTS OF FEDERAL SPECIFICATION TT-P-1952 6 TT-B-1325 APPROXIMATELY 4056 SF @ 0.86/SF $ 3,488.16 OUR TERMS ARE CASH UPON COMPLETION. IF THE CONSTRUCTION PERIOD EXCEEDS 30 DAYS, WE WOULD RECEIVE MONTHLY ESTIMATES FOR WORK IN PLACE LESS 109, RETAINAGE. UPON COMPLETION, ALL MONIES BECOME DUE INCLUDING ANY RETAINAGE. IF OUR PROPOSAL IS ACCEPTABLE, YOUR SIGNATURE BELOW WILL CONSTITUTE A CONTRACT. IF WE CAN BE OF ANY FURTHER HELP, PLEASE FEEL FREE TO CALL. YO/URNS VERY TRULY, DON PHILLIPS SECRETARY H S H MATERIALS ACCEPTED: ZcJC~C ~ ~^~-+ Edd R. Turner, Mayor DATE: ACCEF DATE: /Q~.,.~~~~~ iyy~._. -. BUSYNESS OF THE CITY COUNCIL CITY OF KERRVILLE, TEXAS R3-11-87 SUBJECT: Rehabilitation of Runway 02/20, Louis Schreiner Field KC88-0 FOR AGENDA OF: August 23, 1988 DATE SUBMITTED. August 17, 1988 SUBMITTED BY: Di,~ector of Engineering CLEARANCES ire r of Public EXHIBITS: Change Order No.l, AGENDA MAILED TO: County Commissioners Court APPROVED FOR SUBMITTAL BX CITY MANAGER:,~o'`~ Expenditure Current Balance Amount Account Required: in Account: Budgeted: Number: 512,708.50 838,503.84 5108,500.00 #47-99-00-850 PAYMENT TO BE MADE TO: APPROVED FOR SUBMITTAL BY FINANCE DIRECTOR:,/1 SUMMARY STATEMENT During the rehabilitation of Runway 02/20, the Contractor discovered two areas within the base that showed signs of failure. Failure of the base dccurred during the placement of the new 1 1/2" asphalt surface. Staff consulted with the Testing Laboratozy to determine various options available to correct the base failure. Staff obtaine a proposal for the removal of failed base material and replacement, utilizing concrete as base material and asphalt surfacing. The cost to remove and replace approximately 403 square yards is 512,708.50. The funds to cover this expenditure will come from the current years operating budget. RECOMMENDED ACTION Staff recommends approval of Change Order Number 1 with Materials, Inc, for the Rehabilitation of Runway 02/20, Schreiner Field KC 88-02 and authorize the Mayor to sign Order. xsx Louis the Change l~~( ORDER N0. 18066 APPROVAL OF CHANGE ORDII2 NUMBER 1 WITH H & H MATERIALS, INC. FOR THE REEIABILI- TATION OF RilN4~1Y 02/20, LOUIS SCHREINER FIELD KC 88-02 IN CONCURRINCE WITH THE CITY OF y,ERRVrr,r,F AMID AUTHORIZATION TO SIGN THE CHANGE ORDER IN THE AMOUNT OF $12,708.50 8-25-1988 Vol. Q, Page 634