*Kerr County Software Implementation Schedule*
March Audit and Treasurer (complete)
March 20-24, 2006 – Jail Training at the SO (complete)
March 22-23 Computer Aided Dispatch (CAD) Server installation (complete)
March 27-31, 2006 – Courts classroom training for Criminal, Civil, Probate, and Family at the SO (complete)
April 3-7, 2006 Jail Courts Go Live at each office (delayed one week)
April 3-7 Collections (TAX) classroom training in the District Law Library(complete)
April 10-13 Collections Go-Live (complete)
April 10-13 Jail and Courts Go Live at each office (complete)
April 24-28 - Prosecutor Classroom training in the District Law Library and Go Live at each office. (in progress)
April 24-28 - JP Classroom Training at the Sheriff's Office ( in progress )
May 1,2 Computer Aided Dispatch (CAD) Training at dispatch
May 8-12 Computer Aided Dispatch (CAD) Go Live
May 1-5 - JP Go Live at each office
May 1-4 Law Enforcement classroom training at the Sheriff's Office
May 8-12 Law Enforcement go live
Information Technology Plan for 2005-2009
2005      Desktop computer replacement. Network security improvements. County and District remote office
connectivity.
2006      Network rebuild and Software Group upgrade (Odyssey, Orion, and Incode) rollout. TLETS upgrade. 911
upgrade. Direct Deposit/Timecards.
County-wide training.
2007      Video teleconferencing. E-government on-line payments and public data via the Internet.
2008      VoIP telephone systems, Mobile Data Terminals, integrated law enforcement. Desktop replacement.
2009      Server and Network upgrade. Next Generation Networking (NGN) High speed network connections for multiple offices.
Information Technology Software Upgrade 2005-2006
Project Milestones
Apr      Report on system efficiency
May      Requirements established
Jun      On site demonstrations
Jul      On site demonstrations
Aug      Department approval
Sep      Negotiation of contracts
Oct      Contracts approved
Nov      Contracts executed
Dec      Contracts resubmited, missing signature on addendum
Dec      Financing
Jan      Finance approval. Project Planning.
Feb      Financial and Tax hardware installation
Mar      Financial and Tax data conversion. Financial Go-Live.
Dec      Complete
Electronic Voting Project (Hart Inter Civic)
County Clerk
Dec      Equipment delivery
Dec      Dec 20-23 On site training. COMPLETED
Jan      Jan 5-6 Equipment certification and acceptance. COMPLETED
Feb      Early voting, first election with electronic voting.
Financial (Incode)
Audit and Treasurer
Nov      Survey by mail and database submission
Dec      21st @9am Project Kickoff Meeting in the District Court Jury Room
Jan      Hardware review and order
Feb      Hardware Installation 2/7. Financial data conversion 2/27-3/3/05
Mar      Financial AP GL PR Go Live. Direct Deposit testing
Apr      Direct Deposit and on-line time cards
Tax (Orion)
Nov      Database submission
Dec     
Jan      Equipment rack on site (consolidated with Odyssey rack)
Feb      Hardware intallation
Mar      Database conversion
Apr      Training and go live
May      Complete
Courts (Odyssey)
District Clerk, County Clerk, District Attorneys, County Attorney, Jail, SO and Dispatch
Nov      Database submission
Dec      12th @9am Webex Demo for CAD and calls for service
Jan      13th @all day Project Kickoff Meetings
Jan      long lead equipment ordered and on site. A/C and power installation
Feb      Hardware Installation complete. Database conversion start
Mar      Training and go live Civil and Criminal
Apr      Training and go live Jail, law enforcement, prosecuter
May      Hot checks and jury database conversion and go live. (HC cancel by CA)
Jun      Complete.
Information Technology Completed Projects in 2005
Feb      Tape backup for TSG server. Inventoried and cleaned all PCs. Secured the network
Mar      DATANAS installation for Images. County Attorney's office connected to network. AIX upgrade.
Apr      Wordmerge upgrade. Desktop installation x 32. VPN Server.
May      Domain name change to co.kerr.tx.us with DNS and WWW servers. Computer room re-build.
Jun      High speed Internet connection courthouse and SO. 216 DA on-line. MHMR video teleconferencing.
Jul      Network firewall and secure connections to CH, SO, DA's, JP4/Tax, AP. Identix conversion.
Aug      Civil Fees upgrade. Mail server, DNS, and WWW complete. Cable cleanup Tax and County Clerk.
Sep      VoIP at courthouse and SO. SO network closet re-built. County Court at Law wired.
Oct      Desktop replacement program start, twenty nine computers replaced. Ingram City Marshalls office on line to
county network. Anti-virus and email deployment complete.
Nov      JP4 on-line to county system. Persons database mass-merge, 9000 records. Desktop file server
installed.
Dec      Desktop upgrade and replacement project completed. 198 DA on-line. Initiated TSG upgrades.
Information Technology Completed Projects in 2006
Jan      Land records on-line via Landata. Electronic voting. Computer room improvments, new power and a/c.
County web site pages added and updated.
Jan      Desktop computer automated backup system in place for courthouse and law enforcement center.
Feb      Computer room installation of hardware for Odyssey, Orion and Incode. Legacy Direct Deposit for Payroll
installed.
Mar      Computer network upgrade to Gigabit Ethernet. Software installation and Training. New 911 PSAP.
Interface to KPD. DPS security review completed. Incode financial system installed.
Apr      Incode financial system completed. Tax office Odyssey Software install and go live.
May      County and District clerk Odyssey install and go live.
Jun       Sheriff's Office and Jail Odyssey go live.
Jul      Odyssey deployment and training continued.
Aug      Odyssey release 11 installed. Automated conviction reporting for JP offices on-line.
Sep      Papervision imaging system for District Clerk
Oct      Desktop replacement program year two, twenty seven computers replaced.
Nov      Odyssey Public Access via the Internet completed.
Dec      Desktop replacement complete.
Information Technology Completed Projects in 2007
Jan     
Feb      Voter registration images system transition start.
Mar      Odyssey Hot Checks program canceled by County Attorney.
Apr      Electronic Victim Notifcation 'VINE' program installation.
May      Edoctech system for land records installed. Laserfiche for county clerk installed.
Jun      Laserfiche system on-line. HR and Electronic time reporting project start.
Jul      216th Adult Probation 'Corrections Software' installation.
Aug      216th Adult Probation 'Corrections Software' go live.
Sep      New Livescan fingerprint machine installed. IT Specialist position established and filled.
Oct      Desktop replacement program year three, fifty-five computers replaced.
Nov      County clerk land records imaging started. Juvenile Probation office disconnected from county network.
Dec      Desktop replacement complete. County clerk land records imaging. 216th AP domain conversion. Motor vehicle
computers installed.
Information Technology Completed Projects in 2008
Jan      Odyssey release 13 installed. Juvenile Detention Backup PC and imaging
Feb      GIS project start. SO VPN 'work from home' access.
Mar      Incode version 6 installed. City/County 'broadband services' i.e. microwave project start.
Apr      County Cell phone consolodation complete. 198th Adult Probation network connection.
May      Video Teleconference project start. Incode access for budget. Countywide instant messaging, Spark.
Jun      Video Teleconference and video arraignment system go live. 216th AP Desktop replacement, eighteen computers replaced.
Jul      Large screen monitor installed in commissioners court. Courthouse telephone replacement project start.
Aug      Courthouse and courthouse annex digital video recorder system installation. Backup tape system upgrade.
Sep      Jail Access control system completed. Courthouse DVR system completed. Juvenile Detention door check system. New IT Specialist position.
Oct      Desktop replacement program year four, twenty-eight computers replaced. Gov Deals auction. Internet explorer 7
Nov      Commissioners court cabling, big screen display, and computer systems installation.
Dec      Desktop replacement complete. Adobe 9 deployment.
Information Technology Completed Projects in 2009
Jan      Microwave connection to Animal Control installed. Added office to county network
Feb      Added two terabytes of system storage. Code Red notification system implemented.
Mar      Courthouse access control system completed. Jail and SO high speed network connection upgrade complete.
Apr      Juvenile Detention converted to county network. DPS CJIS Audit completed.
May      E-filing for district and county courts. Incode version 7 upgrade. Road & Bridge, AG Barn added to county network.
May      High Speed network for multiple offices project complete.
Jun      Historical Commission website upgrade. Odyssey on site training and upgrade. Road and bridge software upgrade.
Jul      Odyssey LE and Jail review. Video teleconference for courts expansion. JP Odyssey on site training
Aug      Electronic pollbooks for elections. Odyssey Courts on site training. OCA reporting training and upgrade.
Sep      Odyssey application server add. IT policy review and update.
Oct      Mail, web, dns server replacement. Re-racked the courthouse server room. New livescan fingerprint machines for courtrooms.
Nov      Odyssey new database server. New NAS server, 3TB of storage. New tape loader. Phone system replacement specified.
Dec      Phone system and phone service bid. Odyssey court compliance on site training. New IT Specialist I position.
Dec      Desktop replacement program, twenty-three computers replaced.
Information Technology Completed Projects in 2010
Jan      New Jury software system. Crimestoppers TIPSOFT system. Incode version 8.
Feb      Paperless/scanning project for the auditor.
Mar      New phone system installation begins.
Apr      Courthouse, replaced phone system. Kerr County on line with TDEx Texas Data Exchange.
May      Unified communications, fax, email, messengering. New courthouse phone service provider.
May      Odyssey Jail and LE upgrade. e-Recording for land records. IT policy review.
Jun      Courtroom audio visual equipment project and new video teleconference equipment.
Jul      Extension office, added to network. Ag barn, added to network and phone system.
Aug      Sheriff's Annex new construction. Installed racks, network, phones. OCA reporting makeover on site training.
Sep      Added the Kerrville/Kerr County airport to the county network.
Sep      Moved adult probation, juvenile probation, and CID to new facility.
Oct      Sheriff's office, replaced phone system and service.
Nov      Road and Bridge, Ag Barn, Juvenile Detention phone system implemented.
Dec      New courthouse router. Dual Internet Service Providers.
Information Technology Completed Projects in 2011
Jan      Antivirus and patch management upgrade.
Feb      Desktop replacement program, twenty-seven computers to be replaced.
Mar     
Apr     
May     
May     
Jun     
Jul     
Aug     
Sep     
Oct     
Nov     
Dec